ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Alla Goldner <Alla.Goldner@...>
+1
From: onap-tsc-vote@... <onap-tsc-vote@...>
On Behalf Of Catherine LEFEVRE
Sent: Wednesday, April 24, 2019 11:34 AM To: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
This email and the information contained herein is proprietary and confidential and subject to the Amdocs Email Terms of Service, which you may review at https://www.amdocs.com/about/email-terms-of-service
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
+1
From: onap-tsc-vote@... <onap-tsc-vote@...>
On Behalf Of Catherine LEFEVRE via Lists.Onap.Org
Sent: Wednesday, April 24, 2019 11:34 AM To: onap-tsc-vote@... Cc: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Srini <srinivasa.r.addepalli@...>
+1
From: onap-tsc-vote@... [mailto:onap-tsc-vote@...]
On Behalf Of Catherine LEFEVRE
Sent: Wednesday, April 24, 2019 1:34 AM To: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Chaker Al Hakim <chaker.al.hakim@...>
+1
Regards, Chaker
From: onap-tsc-vote@... [mailto:onap-tsc-vote@...]
On Behalf Of Catherine LEFEVRE
Sent: Wednesday, April 24, 2019 4:34 AM To: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Yang Bin
+1
Best Regards, Bin Yang, Solution Engineering Team, Wind River ONAP Multi-VIM/Cloud PTL Direct +86,10,84777126 Mobile +86,13811391682 Fax +86,10,64398189 Skype: yangbincs993
From: onap-tsc-vote@... [mailto:onap-tsc-vote@...]
On Behalf Of Catherine LEFEVRE
Sent: Wednesday, April 24, 2019 4:34 PM To: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Murat Turpcu <murat.turpcu@...>
+1
Kimden: onap-tsc-vote@... <onap-tsc-vote@...>
Yerine Catherine LEFEVRE
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
+1
Best regards
Von: onap-tsc-vote@... <onap-tsc-vote@...>
Im Auftrag von Catherine LEFEVRE
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Alexis de Talhouet <adetalhouet89@...>
+1
toggle quoted messageShow quoted text
Thanks, Alexis
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Eric Debeau
+1
Best Regards
Eric
De : onap-tsc-vote@... [mailto:onap-tsc-vote@...]
De la part de Alexis de Talhouet
+1
Thanks, Alexis
On Apr 25, 2019, at 6:18 AM, Andreas Geissler <andreas-geissler@...> wrote:
+1
Best regards
Von: onap-tsc-vote@... <onap-tsc-vote@...> Im
Auftrag von Catherine LEFEVRE
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference:
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
_________________________________________________________________________________________________________________________ Ce message et ses pieces jointes peuvent contenir des informations confidentielles ou privilegiees et ne doivent donc pas etre diffuses, exploites ou copies sans autorisation. Si vous avez recu ce message par erreur, veuillez le signaler a l'expediteur et le detruire ainsi que les pieces jointes. Les messages electroniques etant susceptibles d'alteration, Orange decline toute responsabilite si ce message a ete altere, deforme ou falsifie. Merci. This message and its attachments may contain confidential or privileged information that may be protected by law; they should not be distributed, used or copied without authorisation. If you have received this email in error, please notify the sender and delete this message and its attachments. As emails may be altered, Orange is not liable for messages that have been modified, changed or falsified. Thank you.
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Stephen Terrill <stephen.terrill@...>
+1
From: onap-tsc-vote@... <onap-tsc-vote@...>
On Behalf Of Catherine LEFEVRE via Lists.Onap.Org
Sent: Wednesday 24 April 2019 10:34 To: onap-tsc-vote@... Cc: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Ning So <ning.so@...>
+1
Ning
From:
onap-tsc-vote@... <onap-tsc-vote@...>
On Behalf Of Catherine LEFEVRE via Lists.Onap.Org
Sent: Wednesday 24 April 2019 10:34
To: onap-tsc-vote@... Cc: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
Virus Warning: Although the company has taken reasonable precautions to ensure no viruses are present in this email. The company cannot accept responsibility for any loss or damage arising from the use of this email or attachment."
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Chen Yan <13301380182@...>
+1 Regards Yan Chen ------------------ 原始邮件 ------------------ Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125 Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Milind Jalwadi <milindj@...>
+1
From: onap-tsc-vote@... <onap-tsc-vote@...>
On Behalf Of Catherine LEFEVRE
Sent: Wednesday, April 24, 2019 2:04 PM To: onap-tsc-vote@... Subject: [onap-tsc-vote] ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones Importance: High
Good evening/morning TSC (or proxy),
As discussed during the TSC call on 4/18, we will perform an offline vote regarding “ONAP El-Alto Schedule & Focus on Internal Debt/Non-functional requirements and ONAP Frankfurt Release Milestones”.
JIRA Reference: https://jira.onap.org/browse/TSC-125
Please vote no later than April 26th, 2019 End of your Day.
+1 ONAP El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones approved; 0-neutral; -1 El-Alto Schedule/Focus and ONAP Frankfurt Release Milestones not approved;
Many thanks & regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
============================================================================================================================ Disclaimer: This message and the information contained herein is proprietary and confidential and subject to the Tech Mahindra policy statement, you may review the policy at http://www.techmahindra.com/Disclaimer.html externally http://tim.techmahindra.com/tim/disclaimer.html internally within TechMahindra. ============================================================================================================================
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Dear TSC Members (or proxy),
Thank you for your feedback.
If I did not miss any vote, 83% of the TSC team has already voted.
Based on your inputs, we can conclude that the ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones have been approved.
Many thanks and regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Dear TSC Members (or proxy),
Slight update – we were previously missing the vote of our S3P Lead J
If I did not miss any vote, 89% of the TSC team has voted.
Based on your inputs, we can conclude that the ONAP El-Alto Schedule/Focus & ONAP Frankfurt Release Milestones have been approved.
Many thanks and regards Catherine
NOTE: This email (or its attachments) contains information belonging to the sender, which may be confidential. proprietary and/or legally privileged. The information is intended only for the use of the individual(s) or entity(ies) named above. If you are not the intended recipient, you are hereby notified that any disclosure, distribution or taking of any action in reliance on the content of this is strictly forbidden. If you have received this e-mail in error please immediately notify the sender identified above
|
||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|